Materials rise faster than work. What that does to a project budget
The gap between the construction work price index and the material price index reached 2.4 percentage points in July. On fixed-price contracts that comes straight out of the margin.
Work prices rose 4.5 % year on year, materials 6.9 %. The 2.4-point gap is the part of the increase a contractor cannot pass on — unless the contract contains a price adjustment clause.
Month-on-month rates have calmed: work +0.2 %, materials +0.1 %. In the short term the calculation is more predictable than in spring, but the year-on-year gap remains.
The practical conclusion: on contracts running longer than a quarter it makes sense to check the material part of the budget against current price lists rather than those used when the bid was prepared.
Index gap — July 2026
| Work prices | +4,5 % |
| Material prices | +6,9 % |
| Gap | 2,4 b. |
| Work month on month | +0,2 % |
| Materials month on month | +0,1 % |
Sources: CZSO, Producer price indices — July 2026 (17 August 2026), csu.gov.cz.